MUNICIPAL PROJECTS
|
 |
King County Department of Natural Resources
Westpoint Sludge Processing Facility
Completed mechanical piping of two 100 ton dryers, installation of 28
conveyors, odor control system, dust collection system, two steam boilers,
four condensate pumps to de-aerator system, sludge storage tanks, plant
air, control air and process piping. |
| |
US Naval Air Station Whidbey Island: ODS Compliance
Project
Replacement of two chillers in 2547 Building and four chillers in
2700 Building, while maintaining existing cooling system in each building.
Installation of new pumping & control system.
|
| |
King County Department of Natural Resources Westpoint
Oxygen Generation and Dissolution Facility
Removal and reinstallation of 44 control valves up to 36" diameter
in sensitive oxygen environment. Work completed during 10 working
day shutdown of partial system while keeping redundant system in operation.
|
 |
Washington State Dept. of Fish and Wildlife: Issaquah
Hatchery South Side Renovation
Manufacture of Fish Crowders. Installation of new distribution water
system. HDPE piping system sizes 4" - 36". Custom stainless fabrications.
(CLICK ON IMAGE TO ENLARGE)
|
 |
Kitsap County Energy Services
Misc. modification construction to various municipal facilities. Shown:
Sheet Metal Division Foreman working on HVAC unit on top of Kitsap
County Courthouse Building.
(this project is currently in progress)
|
 |
Tolt Water Treatment Facility: Welded
Steel Yard Piping
Perform field installation and welding of steel water lines up to 96"
diameter. |
| |
King County Department of Natural Resources
West Division Capital Improvement Program
Misc. modification construction to various waste treatment facilities. |